Bosch, a world leader in precision mechanics and electrical engineering needed to separate a section of its facility to conduct critical sound testing. This area had to be blocked off from outside noise for accurate results. The enclosed area had to be sound proofed and the walls were required to be class A rated and go from floor to existing ceiling keeping the testing area clean.

The Solution

Faced with multiple challenges such as existing piping, duct work, tight areas and a limited time-frame, Allied’s design team made several site visits and multiple design revisions but ultimately came up with the perfect solution that fit Bosch’s exact needs. The modular tall wall was constructed utilizing our Integra 400 Class A gypsum panels, powder coated aluminum framing and steel insulated doors. Typically, the short time frame required for a complete installation of TallWalls and working around existing obstructions would require additional time. However, Allied’s prefabricated modular wall system allowed the TallWall to be installed quickly, easily meeting the projected deadline.

The Results

After several site visits, and drawing revisions, Bosch’s engineering team finalized a layout that would fit into their space and met their critical timeline. Needless to say, Bosch was happy with the solution, the look and the installation.

Bosch_featured

 


allied_advantage