Company Name:
Gaylord Palms, a resort in Florida.

Solution:
Gaylord Palms needed to erect a temporary movie theater inside their convention hall which would be composed of tall, sound-reducing walls that could reach the ceiling of their facility.

Why modular?
Due to the scheduling of the convention hall, the construction portion of the project had to be done in a slim 48 hours. Also, Gaylord Palms would be able to take down the wall and reuse the modular components for future applications.

 

casestudies-gaylord

 

How did the project go?
Needless to say, judging every phase of the project (design, manufacturing, and shipping) Allied Modular was able to deliver on all counts. Our team put together a tremendous effort to get such a large job done within the aggressive timeframe and our client was very happy with the results.

Was Gaylord Palms happy with the result?
According to Gaylord, they were exceptionally happy with the results, as the building turned out to be exactly what they thought it would be, and in the timeframe required, no less. Consider the conclusion of this project to be the beginning of another great business partnership!